Solutions / T&M and Force Account

Extra work documented the day it happens

Force account and T&M work is where contractors either recover their cost or eat it, and the deciding factor is almost never the merits. It is whether the daily record was created at the time or reconstructed under dispute.

Every civil contractor has a version of this story. The owner's rep directs a change verbally. The crew does the work because the crew is standing there and the schedule does not wait. Three weeks later the ticket goes in, and now there is a negotiation about hours that nobody wrote down at the time.

The problem: the strongest position is a record you did not keep

Force account and time-and-materials work has a documentation burden completely out of proportion to its dollar value. A $9,000 extra can consume more office hours than a $400,000 pay item, because on the pay item nobody disputes what was installed.

The usual failure modes:

On extra work, you are not paid for what you did. You are paid for what you can show you did, in the form and on the timeline the contract requires.

How PM Axsus handles it at the point of installation

PM Axsus does not negotiate your change orders. What it does is make sure that when the negotiation happens, the underlying record was created contemporaneously by the people doing the work.

The same field-capture layers that run your base scope carry the extra work:

None of that is exotic. It is the ordinary discipline of capturing work as it happens, applied to the category of work where sloppy capture is most expensive.

What the office sees

Same day

The extra work is visible now

Hours and resources on extra work surface while the ticket can still be presented promptly.

Assembly

Backup that already exists

Labor, equipment, materials, and photos live on the same project record instead of in four systems.

Exposure

Unbilled extra work

Extra work in progress is visible as cost before it turns into an unpleasant surprise at month end.

Cost picture

Kept out of base scope

Segregated hours keep extra work from silently distorting the earned value on your base pay items.

That last point is underrated. When extra-work hours get buried in base cost codes, two things break at once: the extra is under-billed, and the base scope looks unprofitable. PMs then go chasing a productivity problem that does not exist. Clean segregation fixes both.

An honest limit

Software does not create entitlement. If your contract requires written authorization before extra work begins and you did not get it, no field app fixes that. What field-first capture gives you is the strongest possible factual record, created at the time, in a consistent form, which is what makes a legitimate claim easy to substantiate and an aggressive one easy to defend against.

Where this fits

T&M documentation is built on time tracking and field capture with photos and signatures, and it protects the accuracy of your earned value model. Contractors working under strict public-agency rules should also read the DOT subcontractor page.

Common questions

Does PM Axsus generate the T&M ticket form my owner requires?

Owner ticket formats vary widely and you should confirm the specific form during a demo rather than assume. What the platform provides is the underlying contemporaneous record of labor, equipment, materials, and conditions in structured form, which is the substance every ticket format is asking for.

How do we separate extra-work hours from base scope hours?

By capturing hours against the work being performed at the time, rather than assigning a whole day to one cost code from memory. That is a discipline question as much as a software question, but capture at clock-in is what makes the discipline practical for a foreman.

What if the owner's rep gave verbal direction only?

That is a contract problem, not a software problem, and you should follow your contract's notice provisions. A complete contemporaneous field record of what was done, when, with what resources, materially strengthens your position, but it is not a substitute for required written notice.

Can we see how much unbilled extra work is outstanding?

Extra work captured as it happens shows up as cost on the project record, which is what makes outstanding exposure visible before month end rather than after.

Make your next force account ticket boring

Bring a T&M ticket that turned into a fight and we will walk through what the contemporaneous record would have looked like. Book a demo, or try our free traffic control plan builder.