Solutions / Quantity Tracking

Installed quantity is the number everything else is built on

Earned value, progress billing, production rates, and percent complete all resolve to one question: how much is actually in the ground. PM Axsus captures installed quantity against the pay item at the point of installation.

On a unit-price civil job, quantity is not a reporting detail. It is the product. You are selling linear feet, cubic yards, square yards, and each-counts. Everything the office does with the job is a transformation of the quantity number, which means an error there propagates into billing, cost, schedule, and the next bid.

The problem: quantities are counted twice, late, by different people

The standard process has quantities getting counted at least twice. Once informally by the crew, so they know where they are. Once formally near the end of the pay period, by a PM or engineer working from as-builts, station marks, and phone calls. The two counts rarely match, and the second one is authoritative because it is the one that gets billed.

What goes wrong:

Quantity counted at the end of the month is a billing input. Quantity captured the day it goes in is a management tool. Same number, completely different value.

How PM Axsus handles it at the point of installation

Quantity capture in PM Axsus happens where the quantity is created: at the pipe, at the structure, at the lift. The crew logs what went in, against the pay item and cost code it belongs to, on the day it happened.

Three properties make that useful rather than merely tidy:

From there the transformations are mechanical rather than interpretive. Earned value is the budgeted rate times the installed quantity. Percent complete is installed over planned. Production rate is quantity over the hours captured against the same code. None of those require a separate reporting cycle, because they are all views of one captured fact.

What the office sees

Billing

Pay applications with backup

Installed quantities by item and by date, so the pay app reflects work through the cutoff rather than through the count.

Overruns

Items running long, early

Quantity against bid quantity, visible while there is still time to notify and negotiate.

Progress

Measured percent complete

Percent complete derived from counted work instead of estimated by the person with the most optimism.

Feeds EVM

The earned value input

Installed quantity is exactly what earned value is: budget times work actually performed.

There is a cash-flow argument here that owners of mid-sized contractors tend to appreciate more than PMs do. Billing what you installed, in the period you installed it, with backup attached, shortens the gap between spending money and collecting it. On a $20M-a-year contractor, moving a meaningful share of billing up by two to four weeks is a working-capital change, not a paperwork change.

Where this fits

Quantity tracking is the foundation under earned value management and production tracking, and it pairs with time tracking to make rates computable. For the underlying method applied to dirt, see earned value for dirt work.

Common questions

Does this replace surveyed as-built quantities?

No, and it should not. Survey and as-built measurement remain the authority for final quantities on most contracts. Field-captured quantity is the operational number you manage and bill from during the job, and having it makes reconciling to survey a comparison rather than a reconstruction.

How do we handle partially complete items?

By capturing the physical units that are actually complete rather than assigning a percentage to the item as a whole. Where an item genuinely has stages, capture the stage the work reached. The principle is to record a countable fact instead of an opinion.

Can quantities be tied to our schedule of values?

That is the intent: quantities land against the pay items and cost codes you already bid and bill on. Bring your schedule of values to a demo and check the fit against your actual item structure.

What if the field count and the office count disagree?

They will sometimes, and that is useful information rather than a failure. A dated, attributed field record turns the disagreement into a specific question about a specific day instead of a general argument about whose estimate is better.

Bill what you installed, in the period you installed it

Bring your schedule of values and we will walk through how quantities would be captured and what the pay app backup looks like. Book a demo, or try our free traffic control plan builder.